ACME Solar commissions BESS component of FDRE project at Neemri, Rajashthan
(01 Oct 2026)

Back

ACME Solar Holdings (ASHL), through its wholly-owned subsidiary i.e. ACME Sigma Urja, has commissioned Phase-I of the BESS component, comprising 53.73 MW/222.969 MWh out of 250 MW / 1069 MWh (Discharge Capacity) of the FDRE Project located at Village: Neemri, Tehsil: Rawatbhata, District: Chittorgarh, Rajasthan on 30 September 2026.

At present, only the BESS component of the project has been commissioned, while the corresponding renewable energy generation component is under development. The Commercial operation date (COD) for the same shall be 02 October 2026.